Home
Wheal Agar
Mine Costs
Methods of Payment
Shaft Sinking
Building Eng. Houses
Development Mining
Stoping
Hoisting
Surface Work
Supplies
Doc and Club
Glossary
Contact Me
Links

 

Development Mining

In total there were 76 development headings, (drives, winzes, raises) amounting to 1,835 metres advanced during the life of the Cost Book.

We do not know the cross sectional size of these tunnels, but for the drives we could expect the height in the centre to be barely that of an average man and the width just wide enough for a trammer to work, while the winzes and raises might be 1.5 metres in diameter or less.

Raises
There are only four locations recorded in the Cost Book showing rising, i.e. driving a tunnel upwards.  This is understandable when one considers the effort required for hand boring up-holes, but it is interesting to note that one raise was driven by 4 men in Dobree's lode for 23.78 metres giving an average advance of 7.93 metres per month which is a better performance than most of the drives and winzes.  The cost worked out at £2.14 per metre.

Winzes
Winzes are sunk to connect the main levels within the lodes in preparation for the production, or stoping of the ore.  The main levels from New Engine Shaft in Wheal Agar during the life of the Cost Book were at Adit 36, 48, 60 and 70 fathoms from surface, and from Windstraw Shaft at Adit 33, 40, 50, and 60 fathoms. Winzes also assist ventilation through the mine. 

The average advance per month for sinking winzes was 4.3 metres with costs varying from £2.50 to £4.00 per metre.

Drives
Drives are tunnels driven along the strike of the lode and act as the main 'roads' for access to the stopes and conveying the ore to the shafts. There are 47 locations mentioned in the Cost Book.

The following are some examples:-

Driving the Shallow Adit south (Druid Adit)

  • Total advance 57.93 metres, averaging 5.79 metres per month

  • 2 men in pare.  Net pay to pare for 10 months £52.00

  • Cost per metre including materials £1.03

Drive west from Windstraw shaft on 40 fathom level

  • Total advance 62.93 metres, averaging 5.24 metres per month

  • 4 men in pare.  Net pay to pare for 12 months £149.80

  • Cost per metre including materials £3.16

Drive west from Boundary Shaft on 40 fathom level

  • Total advance 45.91 metres, averaging 6.56 metres per month

  • 4 & 6 men in pare.  Net pay to pare for 7 months £87.44

  • Cost per metre including materials £2.66

Drive east from Windstraw shaft on 50 fathom level

  • Total advance 71.27 metres, averaging 6.48 metres per month

  • 4 & 6 men in pare.  Net pay to pare for 12 months £188.98

  • Cost per metre including materials £3.69

Drive west on North lode 50 fathom level

  • Total advance 82.22 metres, averaging 5.14 metres per month

  • 6 men in pare. Net pay to pare for 16 months £255.12

  • Cost per metre including materials£5.14

Drive west from New Engine shaft on 60 fathom level

  • Total advance 106.12 metres, averaging 5.31 metres per month

  • 4 & 6 men in pare.  Net pay to pare for 20 months £270.83

  • Cost per metre including materials £3.32

Drive west from New Engine shaft on 70 fathom level

  • Total Advance 47.53 metres, averaging 4.32 metres per month

  • 4 & 6 men in pare.  Net pay to pare for 11 months £139.80

  • Cost per metre including materials £3.83

Driving Cross-cut north on the 60 fathom level

A cross-cut is a tunnel driven at right angles to the strike of the lode and is therefore usually in harder waste rock

  • Total advance 22.21 metres, averaging 3.70 metres per month

  • 4 men in pare.  Net pay to pare for 6 months £62.00

  • Cost per metre including materials £3.90

Driving  south on the the 70 fathom level crosscourse

A crosscourse is a fissure, with or without any metalic content, cutting across the usual direction of the main lodes. At Wheal Agar it is clear that the particular crosscourse contained some soft material to make driving less difficult.

  • Total advance 59.19 metres, averaging 8.46 metres per month

  • 2 & 6 men in pare.  Net pay to pare for 7 months £75.21

  • Cost per metre including materials £ 1.66

 

The above are but a few of the work locations underground but they can be considered as being representative of the whole.  It is interesting to note that 25% of the 76 development headings were only worked for one month or less, which may be indicative of differing opinions regarding the best mine planning.

Ventilation must have been bad especially in the new areas of the mine before connections were made to other workings.  In the Cost Book there are only a few references to ventilation and air sollars.The clearest is in December 1858 when the 4 man pare of Francis Cocking & Co. were driving the 60 fathom level east on south lode and the entry states 'putting in air sollars 26 fathoms at 8d' (pence), which amounted to an extra £0.87 in their pay.

Back to top

© John Higgins 2004 This page was last edited on 06/12/2004 Managed by Sounds Exciting